A developer has just shown a huge win. Morro quickly got approval for their housing plan. This scheme has 150 homes. It received Gateway 2 approval very fast. This decision came from the Building Safety Regulator (BSR). Crucially, it is a big moment for builders. Specifically, the approval took only 13 weeks. In fact, this is just one week more than the BSR’s target. Therefore, this success sets a strong example for navigating BSR Gateway 2.
The news is very welcome. In fact, it follows months of industry delays. Developers faced big hold ups under the new system. Reasons varied. For example, applications were poor. Guidance from the regulator was unclear. However, this fast approval shows the system works better now. Furthermore, it highlights that BSR changes are paying off.
I. The Challenge: Why BSR Gateway 2 Was So Slow Before

The Gateway system is a core part of the Building Safety Act (BSA). Specifically, it creates check points for tall homes (HRBs). Gateway 2 is the main check. Essentially, BSR must approve it. This must happen before any building work starts.
Initially, this new, strict system caused major problems as previously reported. Consequently, the BSR reported long waiting times. For instance, the average wait time reached 36 weeks at one point. This was three times the target. The backlog happened for many reasons:
- Application Quality: First, many early applications lacked detail. In other words, they did not show how designs met safety rules.
- Capacity: Second, the BSR needed time to hire and train its teams (MDTs). These teams check complex plans.
- Clarity: Third, the industry was unclear on BSR rules. Consequently, this confusion caused problems. Thus, builders and the regulator were frustrated.
Therefore, the Hackney scheme’s fast approval is huge. In short, it offers a clear, positive case.
II. The Benchmark: Morro’s 13-Week Success
Morro’s success is a major step. Indeed, getting approval in just 13 weeks is a strong signal. It shows the BSR target of 12 weeks is possible.
Adam Brockley, Morro founder, noted the impact. He said: “Securing Gateway 2 approval… is a big moment for developers.” Specifically, this confidence is vital for build-to-rent. They need to deliver new UK homes fast.
Furthermore, the success came from key rules:
- Collaboration: Firstly, the project team worked closely with the BSR. Also, they talked to the local Fire Authority.
- Communication: Secondly, clear talks helped solve issues fast.
- Quality Processes: Thirdly, they sent in a high-quality, full application. This was key.
Kuli Bajwa of Pareto Projects noted the change. He said: “The BSR is more responsive now. We feel we are finally being heard.” Thus, this result proves what is possible. It shows that clear rules and shared safety goals work.
III. BSR’s New Tools: Driving Speed in BSR Gateway 2

The BSR has fixed the slow start. Consequently, the HSE confirmed they made changes. Importantly, these changes aim to speed up decisions. The Morro success shows this is working.
A. The Innovation Unit (IU)
The BSR created a new team: the Innovation Unit (IU).
- Purpose: Specifically, this unit is a dedicated team. It includes inspectors and technical engineers.
- Goal: Therefore, it handles new, complex plans. The IU is strict. It quickly checks or rejects poor applications. This forces developers to fix issues fast. Furthermore, this stops bad applications from causing delays.
Recent data shows the IU is helping. In fact, it manages many new build applications. Most now meet the 12-week deadline.
B. Record Approvals with Requirements
BSR data (up to November 2025) showed good progress.
- Approval with Requirements: Moreover, the BSR issued many approvals this way. This method allows the BSR to approve a design. However, it adds specific rules. These must be met before building continues. Ultimately, this helps start projects faster.
- Backlog Reduction: Furthermore, the regulator is hopeful about clearing its backlog. They confirmed their targets are achievable.
Therefore, the IU’s focused work and the ‘approval with requirements’ route are clearly speeding up BSR Gateway 2.
IV. Lessons Learned: Setting a New BSR Gateway 2 Standard
The Morro case offers clear lessons for everyone on tall home projects:
A. The Dutyholder Mindset
The biggest change is mindset. The BSA puts legal duties on the Client and others. Consequently, the Morro team understood this. They focused on proving safety, not just claiming it.
The old system needed less detail early on. In contrast, the BSR Gateway 2 demands a “golden thread” of information. This thread must show clear safety and accountability from day one. Therefore, the Morro team focused on quality. They did detailed design work early.
B. Early Engagement is Key
The project succeeded due to strong, early talks. Specifically, this means talking to the BSR and fire authorities early. This helps to:
- Identify Issues: First, it finds potential problems before the formal submission.
- Build Trust: Second, it builds a strong link with the regulator.
Thus, this forward looking approach, instead of waiting for BSR comments, clearly sped up the final decision.
C. Full Submission Quality
Developers must treat the Gateway 2 application as a complete safety plan. It must clearly show proof of compliance in all areas:
- Fire Strategy
- Structure
- Façades (outside walls)
- Building Services
In conclusion, Morro’s success shows that a high-quality, full submission, coupled with good communication, cuts approval times.
Conclusion: A Clear Path Forward for BSR Gateway 2
Morro’s success is a turning point. It proves the BSR Gateway 2 system can work well. Getting approval in 13 weeks is close to the target. This shows that the BSR’s changes are having a good effect.
The wider data supports this trend. Because of the Innovation Unit and the ‘approval with requirements’ route, the BSR is reducing its backlog. However, the industry must help. Therefore, developers must learn from Morro. They must embrace teamwork, send in high quality applications, and talk early.
Ultimately, this major step gives confidence. It shows investors and developers that the new safety rules can help build homes. It offers a working model for navigating BSR Gateway 2 fast.
Source Verification: The details regarding Morro, the 13 week approval time, the BSR’s Innovation Unit, and the record number of ‘approval with requirements’ decisions are verified by reports from Construction Enquirer, Building, and the Fire Protection Association (FPA) referencing BSR data up to November 2025.